Good news at last - Site Start dates

After a while getting permits, approvals and everything just right we eventually got the good news of a site start. In late December we were advised of the potential of our build starting in Mid Jan. I wasn't overly confident but arranged for our block to be mowed and cleared just in case. Jump forward a few weeks to today and Porter Davis have come through with the goods. We have a site start set with the site cut booked for 19th Jan 2017 and as long as weather permits we will then have a slab pour on 2nd Feb 2017. Going by our contract time we will be in no later than mid September 2017. Lets see how it all pans out. Christmas lunch at our place this year I say!