I am constantly amazed how quickly things are done. The frame takes no time, plaster was only a day to hang and the floor and wall tiles will be about 3 days start to finish. The tilers arrived, cleaned up and set out for a few hours one afternoon. The next day they layed pretty much all of the full floor tile (no cut tiles). Then followed that up with a day filling all the cut tiles space and installed most of the wall tiles. Another day with a few hours of grouting and they are mostly done. They will be finished with about another half day completing our feature tiles kitchen splashback and the remaining grout.