Sunday, 1 October 2017

External Tiles Installed.

Late last week the external tiles were layed. The external area where tiles go are just the standard areas - front Balcony and rear Terrace, When going through the colour selections at World of Style you get the option to add tiling to the other outdoor areas if you would like too.

Wednesday, 9 August 2017

Plumbing Fitoff done!

The fit off plumbers have returned to complete the fit off of taps and basins. Over the last week or so there have been a couple of visits to complete the various plumbing tasks. They still haven't completed the taps in the master ensuite because there was an alignment issue that was fixed. All of the toilets, basins, sinks and external taps have been plumbed and are now operational.

Monday, 19 June 2017

Tiles are a go!

I am constantly amazed how quickly things are done. The frame takes no time, plaster was only a day to hang and the floor and wall tiles will be about 3 days start to finish. The tilers arrived, cleaned up and set out for a few hours one afternoon. The next day they layed pretty much all of the full floor tile (no cut tiles). Then followed that up with a day filling all the cut tiles space and installed most of the wall tiles. Another day with a few hours of grouting and they are mostly done. They will be finished with about another half day completing our feature tiles kitchen splashback and the remaining grout.