Saturday, 29 July 2017

Security System

For our security system we chose to have it mostly installed as part of the build. I looked at options to install after handover but everything offered was wireless. I didn't like the idea of replacing batteries on all of the sensors every year or so. Or not getting around to it and the alarm has a bypassed sensor zone while the battery is flat. Getting it installed with Porter Davis meant that all of the sensors would be wired, it would be operational from day 1 and I wouldn't have to worry about flat batteries. It seemed the better choice.

Thursday, 27 July 2017

Bricks - Have Finished... Almost

It seems that things get finished to about 90% or so and then there is some sort of delay or reason it can't be finished. The brickwork took some time to get moving and started and stopped several times along the way. The main issue was with colour matching and but now we are complete... Actually we're not complete. The brickies can't complete the brickwork because there is scaffolding on the house and the garage space is covered with materials required to build our house. Ohh well, progress is still moving fairly quickly so we are happy either way.

Tuesday, 18 July 2017

Wardrobe Fitouts & Cubboards, Pantry etc

There are several suppliers of similar items when you build. For example; Electrical, Data, Alarm & TV/Phone prewire were done by 3 different teams on our build at 4 different times.  Then, I assume, they will all come back at similar but different times to complete their fitoff.

Monday, 17 July 2017

Painting is almost complete.

I still find it really interesting that it seems like nothing much happens to a certain part then in the blink of an eye painting if finished - well almost. It's about a month ago that our painting first started and after a few hold ups because of other things going on,

Tuesday, 27 June 2017

Feature Tiles & Tiling is complete - Almost

So its been a bit over a week but the tiles are mostly finished. The tilers came and went a couple of times finishing and fixing a few areas. Our master bathroom had the taps placed in the wrong position so the tillers have to wait until that gets fixed. Our feature tiles have been installed in the shower niches and powder room. Wall tiles in the kitchen and other areas.

Monday, 19 June 2017

Tiles are a go!

I am constantly amazed how quickly things are done. The frame takes no time, plaster was only a day to hang and the floor and wall tiles will be about 3 days start to finish. The tilers arrived, cleaned up and set out for a few hours one afternoon. The next day they layed pretty much all of the full floor tile (no cut tiles). Then followed that up with a day filling all the cut tiles space and installed most of the wall tiles. Another day with a few hours of grouting and they are mostly done. They will be finished with about another half day completing our feature tiles kitchen splashback and the remaining grout.

Saturday, 17 June 2017

Site Supervisor

For those of you that don't know, you get allocated a site supervisor that will look after your build once the slab has been competed. If everything goes to plan you shouldn't have to much communication with you Building Coordinator once the construction stage starts.