Cornices & Plaster finishing
The plaster finishing took about 2 to 2.5 days. They installed the internal and external corners on walls, ceiling and bulkheads. Patched all of the joints and filled all of the joints and other areas that required finishing. Sanding of the filler was done a couple of days later.
Labels:
Colour Selection,
cornice,
plaster,
sanding,
selections,
stopping
Sunday, 23 April 2017
Plaster - Wow that was quick!
Monday, 17 April 2017
To pipe lag or not to pipe lag, that is the question
"acoustic pipe and duct lagging. Soundlag™ is a high-performance composite acoustic lagging product developed to reduce noise from pipes, valves, fan housings, and ductwork in commercial, industrial and domestic buildings."
Labels:
Bradforms Soundscreen,
Insulation,
Lagging,
Noise,
Pipe Lagging,
Plumbing,
Supervisor
Friday, 14 April 2017
Insulation & Sound "Proofing"
Thursday, 13 April 2017
Let there be noggins!
When we were visiting established homes for sale prior to deciding to build I noticed something that was fairly consistent in a lot of houses. I would often see issues where towel rails, toilet rolls holders and other items had come loose due to insufficient grip where there is no noggin or stud to attach to. I am quite particular when it comes to this sort of thing and it appears Porter Davis are too.
Saturday, 8 April 2017
Rough In - Electrical and Data.
The electrical rough in appeared to be fairly straight forward. A couple of days drilling holes and routing wires through the ceiling and wall spaces to all of the locations we had selected. We had added quite a few extras when it came to electrical with 74 downlights, numerous powerpoints added and several 2 way switches. We also made provision for lighting and electrical expansion into our outdoor space once that is constructed later on.
Labels:
3 Phase,
Cameras,
Data,
Electrical,
Internet,
NBN,
Prewire,
Rough in,
Speakers,
Supervisor
Friday, 7 April 2017
Roouggghhh In's!
We've had a bunch of rough in's done over the last few weeks or so.
Labels:
3 Phase,
Air Conditioning,
Ducted Vacuum,
Gas,
Mess,
Plumbing,
Water